Apostles trail continues

WORK continues on stage one of the Twelve Apostles Trail Project.

By Support Team

Project progresses: Work is progressing on the long-awaited for 12 Apostles Trail.
Project progresses: Work is progressing on the long-awaited for 12 Apostles Trail.

WORK continues on stage one of the Twelve Apostles Trail Project.

Following on from the Christmas period shutdown work has been restarted with a number of parts of the project completed including:

 Concrete path and pavement works at the car park lookout;

 Earthworks and fencing for part of the concrete path east of the Great Ocean Road lookout;

 Works at the Desailly Street/Lord Street intersection and the Great Ocean Road lookout are continuing;

 Approval from Telstra for a plan to protect assets;

 Approaches and retaining wall at Gristede’s cattle underpass; and

 All cattle underpass bridges installed.

Upcoming works include:

 Completing the lookout car park;

 Landscaping at Desailly Street and McCue Street intersections will take place after civil works are completed in March;

 Approaches on all cattle underpass bridges to align smoothly with trail;

 Continue construction works to path east of the Great Ocean Road lookout;

 Clearing vegetation between the Campbells Creek bridge and the bus shelter; and

 Repair works on trail where scouring has occurred on sections of trail on North South Road and Timboon Peterborough Road.

The project received $4.5 million from the state government’s Building Works package and $800,000 from the Federal Local Roads and Community Infrastructure program.