General News
29 August, 2023
Final stage for trail
THE Twelve Apostles Trail is in the final stage of works.

THE Twelve Apostles Trail is in the final stage of works.
In recent weeks contractors have completed a number of components of the project including:
• Construction of Campbells Creek bridge footings;
• Kerb and channel poured on Great Ocean Road, east of Campbells Creek bridge;
• Started fencing works on east side of Campbells Creek bridge, with holes cut for fencing;
• Continued path construction and fencing on the east of the Great Ocean Road lookout;
• Wannon Water sewer pipeline completed and tested; and
• Seating installed at lookout carpark.
The final project pieces to be completed are:
• Offisite fabrication of cantilever boardwalk for north of the lookout;
• Landscaping at Great Ocean Road lookout car park and Desailly Street traffic island;
• Continue path construction works between Great Ocean Road lookout and Campbells Creek;
• Complete underground drain construction near bus shelter;
• Campbells Creek bridge to be erected;
• Finalise shop drawings for boardwalks opposite Port Campbell-Curdievale Road and on Great Ocean Road between cutting and Campbells Creek;
• Drainage improvement works on North South Road; and
• Replace missing trail related road signs.