First wind turbine for Mortlake

WIND Farm developer ACCIONA began erection of the first wind turbine at Mortlake South Wind Farm last Tuesday.

By Support Team

Installation: Construction began on the first wind turbine at Mortlake South Wind Farm last week.
Installation: Construction began on the first wind turbine at Mortlake South Wind Farm last week.

WIND Farm developer ACCIONA began erection of the first wind turbine at Mortlake South Wind Farm last Tuesday.

The 35 wind turbines, with a hub height of 105m above ground, will be erected between now and April 2021.

One main crane is currently operating and will be joined by a second during December.

On average, each crane will complete the installation of one turbine per week.

Developer ACCIONA said each turbine being installed was the latest technology with each turbine capable of producing 4.5MW of clean energy, the highest output of any wind turbine currently operational in Australia.

The installation of the first turbine at Mortlake South Wind Farm is expected to be completed over the coming days.

Installation of the first tower at the Mortlake South Wind farm began last week.
Installation of the first tower at the Mortlake South Wind farm began last week.